LOCATION
- Reserve 32727, Strettle Road, Mahogany Creek
PROPOSED WORKS
- Firebreaks (maintain / upgrade)
- Fuel Load Reduction (forestry mulching)
- Planned Burns (multiple cells), supported by local Volunteer Fire Brigades
STATUS OF WORKS
- Firebreaks - Complete
- Forestry Mulching - Complete
- East-North-East Cell - Complete
- Eastern Cell - Complete
- Western Cell (near Kenmore Road) - Proposed
17 April 2026(update: 22 April 2026)
DFES HRB: For further enquiries please contact DFES State Bushfire Mitigation - SBM@DFES.wa.gov.au
LOCATION
- Liberton Road, Chidlow - to the west (south of Cleaver Street through to the Powerline Track)
WORKS
- 70ha Hazard Reduction Burn
STATUS OF WORKS
- Undertaken: Tuesday 19 May, 2026
LOCATION
- Reserve 34765, adjacent to Chidlow Primary School
WORKS (SIZE)
- Hazard Reduction Burning (~4ha)
- Letter to Residents
- Map of HRB
STATUS OF WORKS
- Planned: Either July or September School Holidays
LOCATION
- Reserve 40820, adjacent to Chidlow Playgroup, Chidlow
WORKS (SIZE)
- Firebreaks (1.1km)
STATUS OF WORKS
- COMPLETE: October 2025
LOCATION
- Reserve 34765, adjacent to Chidlow Primary School
WORKS (SIZE)
- Firebreaks (0.75km)
- Mechanical works (2ha)
STATUS OF WORKS
- COMPLETE: October 2025
LOCATION
- Reserve 38367, Cookes Brook, Chidlow
WORKS (SIZE)
- Firebreaks (2.4km)
- Mechanical works (6.7ha)
STATUS OF WORKS
- Complete
LOCATION
- Reserves 9516 and 10636, Bega Street - Burton Road, Darlington
WORKS (SIZE)
- Chemical works (0.5ha)
- Letter to Residents
STATUS OF WORKS
- COMPLETE: Event 1, September, 2025
- COMPLETE: Event 2, December / January, 2025/26
- COMPLETE: Event 3, March / April , 2026
LOCATION
- Reserve 1847, Binbrook Park, Darlington
WORKS (SIZE)
- Firebreaks (2km)
- Mechanical works (1.9ha)
- Letter to Residents
STATUS OF WORKS
- COMPLETE: February 2026
LOCATION
- Reserve 28501, Mitchell Road, Darlington
WORKS (SIZE)
- Firebreaks (0.9km)
- Mechanical works (0.4ha)
STATUS OF WORKS
- Complete
LOCATION
- Reserve 33079, adjacent to Mandoon Close, Darlington
WORKS (SIZE)
- Firebreaks (0.2km)
- Mechanical works (0.6ha)
- Letter to Residents
STATUS OF WORKS
- COMPLETE: 6 December 2025
DFES MAINTENANCE WORKS
- For further enquiries please contact DFES State Bushfire Mitigation - SBM@DFES.wa.gov.au
LOCATION
- Crown Land on Marnie Road, Glen Forrest (see map)
WORKS
- Firebreak maintenance and removal of woody weeds
STATUS OF WORKS
- Proposed: between May and July 2026
LOCATION
Reserve 37708, Railway Reserve Heritage Trail, Harold Street (Creekline)
WORKS
Hand removal and forestry mulching of invasive weed species, including blackberry (Rubus fruticosus aggregate), pampas grass (Cortaderia selloana), false bamboo (Arundo donax), Sydney golden wattle (Acacia longifolia) and black wattle (Acacia mearnsii).
STATUS OF WORKS
COMPLETE (May 2026)
LOCATION
- Marnie Road, verges from Helena College to Lionel Road, Glen Forrest
- Letter to residents
WORKS (SIZE)
- Mechanical works (1.5ha)
STATUS OF WORKS
- Complete, April 2026
DFES WORKS
LOCATION
- Thomas Road & Bailey Road, Glen Forrest
PROPOSED WORKS
- Forestry mulching between verge and firebreaks
- Letter to Residents
STATUS OF WORKS
- Scheduled between February and June 2026
For further enquiries please contact DFES State Bushfire Mitigation - SBM@DFES.wa.gov.au
LOCATION
- Reserve 12453, Falls Park, Hovea
WORKS (SIZE)
- Firebreaks (3.2km)
- Mechanical works (2ha)
STATUS OF WORKS
- COMPLETE: October, 2025
LOCATION
- Verges, from Quail Street down to Alison Street
WORKS (SIZE)
- Mechanical works (5.7ha) with traffic management
- Letter to Residents
STATUS OF WORKS
- COMPLETE: 27 November, 2025
LOCATION
Reserve 38310, Houston Street, Mount Helena
WORKS
Firebreak Upgrade
STATUS OF WORKS
Complete
LOCATION
- Reserve 29269, Mt Helena
WORKS (SIZE)
- Firebreaks (10.4km)
STATUS OF WORKS
- Complete
LOCATION
Reserve 32484, Railway Reserve Heritage Trail, Stoneville to Sexton (Traylen Road)
WORKS
Spraying
STATUS OF WORKS
Assigned
LOCATION
-
Reserve 34095, corner of Coppin and Thomas Rd's in Mundaring
WORKS
-
Woody weed removal via hand cutting and chipping.
-
Spot spraying of invasive species throughout reserve
STATUS OF WORKS
-
Complete (additional works proposed for 2026-2027)
LOCATION
- Reserve 43993, Mardo Reserve, adjacent to Mundaring Primary School
WORKS (SIZE)
- Hazard Reduction Burn (2ha) supported by local Volunteer Fire Brigades
STATUS OF WORKS
- Complete
LOCATION
- Reserve 7045, adjacent to Mundaring Arena
WORKS (SIZE)
- Firebreaks (0.3km)
- Mechanical works (2.6ha)
STATUS OF WORKS
- Firebreaks: Complete.
- Mechanical Works: Complete
LOCATION
Reserve 40921, Meadow Lane, Parkerville
WORKS
Spraying
STATUS OF WORKS
Complete
LOCATION
- Fire access response track from Marshwood Place to Jamroz Court, Sawyers Valley
WORKS (SIZE)
- Fire access response track (0.753km)
STATUS OF WORKS
- FORECAST: Pending permits and approvals
LOCATION
Reserve 32484, Railway Reserve Heritage Trail, Stoneville to Sexton (Traylen Road)
PROPOSED WORKS
Spraying
STATUS OF WORKS
Complete
LOCATION
- Reserve 22843, Riley Road, Stoneville
WORKS (SIZE)
- Letter to Residents
- Firebreaks (2.5km)
- Mechanical works (2.5ha)
- Chemical works (11.3ha)
- Chemical works (11.3ha)
- Chemical works (11.3ha)
STATUS OF WORKS
- Firebreaks COMPLETE
- Mechanical works COMPLETE
- Chemical works (3 applications) - COMPLETE
LOCATION
- Verges along Bailup, Rahnie and Werribee Roads, which were impacted by the 2021 fire
WORKS (SIZE)
- Verges (21.7ha)
STATUS OF WORKS
- Complete, December 2025
LOCATION
- Reserve 39853, Dunham Glen x Needham Road, Wooroloo
WORKS
- Planned Burn, supported by local Volunteer Fire Brigades
STATUS OF WORKS
- Northern Cell - Completed in 2025
- Southern Cell - Proposed 6 May 2026 (click here for more information)